Summary
The sewer main reroute through the riverfront frees up Water Street properties for future development and gets the project shovel-ready for state grant money — but the price tag has grown from $4.1 million to $11.4 million.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Jul 27, 2026.
Impact analysis
Project cost has grown to $11.4 million; tonight's amendment adds $195,000 in engineering.
Future development on Water Street and the city's grant prospects.
Mentions & discussions (4)
Special Work Session & Common Council Meeting - Jul 27, 2026
The city is chasing state WIIA grant money for an $11.3 million sewer pumping station and piping project to fix aging infrastructure and reduce sewer overflows on Lower South Street. The 25% grant share is offset by other grants, so the project depends heavily on outside funding.
Work Session and Common Council Meeting - Jul 13, 2026
The sewer line replacement project's cost has grown from $4.3 million to $11.4 million; the city is scrambling for additional grant funding with an application due July 27.
Work Session and Common Council Meeting - May 11, 2026
The city will apply for a state wastewater planning grant to find and fix areas where rainwater is overwhelming the sanitary sewer system.
Work Session and Common Council Meeting - Apr 27, 2026
The sewer main reroute through the riverfront frees up Water Street properties for future development and gets the project shovel-ready for state grant money — but the price tag has grown from $4.1 million to $11.4 million.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Peekskill
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.